bull-whip effect
学び始める
small order changes in downstream demand lead to large upstream variation -> high unwanted inventories
lumpy demand effect
学び始める
Rip systems not first for unexpected, high demands
unreliability effect
学び始める
FG product consists of 5 parts, each of availability of 95%, then FG availability 77%
BOM
学び始める
bills of material
special BOMs
学び始める
modular bills, planning bills, phantom bills (used for subassies that exist temporarily
MRP requirements
学び始める
computer system necessary, mainly discrete products, accurate bill-of-material, accurate inventory status, stable lead time, problem with frequent re-planning
Four periods in the Rolling MPS
学び始める
Frozen - until week 4, new orders cannot enter and we can't change them; Firm - orders confirmed by customers; Full - we can shift things; Open - we can still assemble orders, we don't have to plan yet